Wednesday, 1 March 2017
Calling times for The Final Delivery
11:30 - 12:30
- Camera, Sound and Lighting crew needed
Get all gear and props ready and up to the Salvation room
Set up for needed Scene's
Begin setting up gear
12:30 - 1:20 (1:50 Latest)
- Camera, Sound and Lighting crew needed
Finish setting gear up (Includes lighting etc)
Overlook script etc and shots
Prepare anything else needed
1:20 - 1:50
- Crew needed
Sound, Lighting and Camera test
1:50 - 3:10
- Actors and Crew needed
Start getting required shots
3:10 - 3:30
- Actors and Crew needed
Get last shots
Re-do some shots if wanted
3:30 - 3:40
- Crew needed
Pack up the gear
Deconstruct set
Vacate the area